Capital Monitoring Q1 2017-18

Meeting: 13/09/2017 - Scrutiny Committee (Item 18)

18 2017/18 Quarter 1 Capital Budget Monitoring Report pdf icon PDF 138 KB

To consider Capital Budget Monitoring in Q1 of 2017/18.

Additional documents:

Minutes:

Howard Hamilton-Smith presented the report which detailed the Council’s capital expenditure and resources position for Quarter 1 up to 30th June 2017.

 

IT WAS AGREED

 

That the report be noted.


Meeting: 15/08/2017 - Executive (Item 23)

23 Capital Monitoring Q1 2017-18 pdf icon PDF 138 KB

To consider a report on Capital Monitoring Q1 2017-18.

Additional documents:

Minutes:

Purpose

 

To provide Members with an update on capital expenditure and resources position along with highlighting any variances

 

Reason for Decision

To effectively manage the 2017/18 capital programme.

 

 

 

Decision

 

(1)  That Full Council be recommended to approve the revised capital budget for 2017/18 totalling £15,589,217, as outlined in Appendix 2;

 

(2)  That Full Council be recommended to approve the proposed financing of the revised capital budget totalling £15,589,217 as shown in Appendix 3;

 

(3)  That the latest estimated year end position on capital receipts and contributions showing an assumed balance of £2,231,605 at 31st March 2018, in Appendix 4, be noted;

 

(4)  That Full Council be recommended to approve a new Capital Scheme for the Calder Park Sport & Play Equipment, totalling £13,700, funded from 3rd Party Contributions and Ward Opportunities Fund; and 

 

(5)  That Full Council be recommended to approve a new Capital Scheme for the Brun Valley Forest Park, totalling £10,486, funded from 3rd Party Contributions.